With the construction process of ultra - high voltage ( UHV) AC power grid and the completion of Jinsu,Fufeng and Xizhe HVDC transmission lines,Sichuan power grid will form a pattern of AC/DC hybrid power delivery. Aiming at the situation of power transfer after UHV DC blocking and combined with the construction process of UHV AC power grid,the AC sections which have a strong coupling relationship with UHV DC is analyzed,which provides guidance for the safe and stable operation of Sichuan power grid.
参考文献
相似文献
引证文献
引用本文
李旻,周启航,邱丽萍,程振龙.特高压交流电网建设进程对四川特高压直流与相关交流断面耦合关系的影响[J].四川电力技术,2013,36(6):13-16. 李旻,周启航,邱丽萍,程振龙.[J]. SICHUAN ELECTRIC POWER TECHNOLOGY,2013,36(6):13-16.